Crew had to replace 1800 feet of fiber between manholes.  One conduit collapsed delaying fiber being pulled in.  Then, they had to finish off with splicing all 288 fibers at each manhole.

There’s a lot more detailed information, but this is for those of you that are curious.

Last splices at 8:30am…